Variety of delays push road projects back to 2010
Late ‘quarterly’ report shows plans off schedule
Wednesday, Aug. 6, 2008
|
| ||
|
A combination of delays due to construction problems, slow right of way acquisition and environmental permitting has pushed the completion of Charles County’s enhanced transportation program out to 2010.
Planning officials last week delivered their first quarterly report on the collection of 14 road projects since February 2007, which revealed that the program’s seven remaining projects are two to three years behind schedule.
There has been a lot of progress in the 16 months since the last report. The county has completed four projects in the interim for a total of seven completed projects. Another project, Rosewick Road Phase 2, is under construction.
The county has also made strides in the area of property acquisition, securing 211 (83 percent) of the 254 properties needed for the roads. This is up from 193 properties (76 percent) in early 2007. Two projects are still awaiting rights of way.
The county’s seven remaining projects are trailing far behind their target completion dates.
Acton Lane Phase 2 is facing delays from right of way acquisition and budget-busting construction bids. It is currently two and a half years behind schedule and scheduled for a September 2009 completion.
Rosewick Road Phase 2 is facing delays from infrastructure relocation. Weak soil problems have also pushed the project $1.3 million (23 percent) over budget. The project is two years behind and shooting for an April 2009 completion.
Western Parkway Phases 2 and 3 have been hampered by efforts to engineer intersections with U.S. 301 and also by the U.S. Army Corps of Engineers wetlands permitting process.
The project’s completion date has been pushed back two years to September 2010.
The corps and the county’s environmental community are also standing in the way of Phases 5, 6, and 7 of the cross-county connector. The agency held a public hearing Thursday night on whether or not to require the county to complete an environmental impact statement for the fragile Mattawoman Creek, through which the road would be built. (See story, Page A-1)
The EIS process would take one to two years.
According to Melvin C. Beall, director of planning and growth management, the corps should provide the county with a decision within 40 days after the hearing.
The connector’s completion date has been pushed back two years to fall 2010.
The county did not respond to an inquiry about whether this date accounts for a possible EIS or just the tight fiscal situation the county faces.
Planning and finance officials have been before the commissioners several times this year requesting budget transfers between projects in an effort to keep the road program moving. This week, the commissioners approved the transfer of $680,000 to boost the Acton Lane Phase 3 construction budget.
Beall told the commissioners that staff would soon bring a proposal to the commissioners to comprehensively reshuffle money in each project.
‘‘A lot of projects have run into various snags,” County Administrator Paul W. Comfort added.
